Module 03 · Pressure Parts and Heat Recovery5 min read

Boiler Shell, Drums, Furnace and Tubes: The Pressure Parts

The pressure parts are the parts that hold steam and water under pressure: the shell or drums, the furnace, the tubes and the plates that join them. They are what the regulations inspect, what a hydraulic test proves, and what fails if the boiler is mistreated.

ByShikhar Singh·Steam Consultant & IT Consultant·Published

You'll learn

  • Name the pressure parts and what each does
  • Explain why wall thickness depends on diameter and pressure
  • Understand why furnaces are corrugated and tubes are small
  • Recognize the ways pressure parts fail

Before this: Fire tube, water tube and smoke-cum-water tube

BeginnerThe idea in plain words, and where you meet it. No maths.

The parts that hold the pressure

  • Shell: the large cylinder of a fire tube boiler, holding the water, the steam space and the tubes.
  • Drums: the steam drum (and sometimes a mud drum) of a water tube boiler, where steam separates from water and sludge collects.
  • Furnace: where the fuel burns. In a shell boiler it is a large tube inside the shell; in a water tube boiler its walls are rows of tubes.
  • Tubes: fire tubes carry hot gas through the water; water tubes carry water through the hot gas.
  • Tube plates and headers: the thick plates or pipes the tubes are fixed into.

Everything else, from fans to controls, can be replaced on the run. The pressure parts are the boiler, in the eyes of the law: they carry the registration number, they are what an inspector examines, and they are what a hydraulic test pressurizes.

IntermediateThe formula, its units, and a worked example on real plant numbers.

Why thickness grows with diameter

Pressure inside a cylinder tries to split it along its length. The stress in the wall, called hoop stress, grows with pressure and with diameter, and falls as the wall gets thicker:

Hoop stress in a thin cylinder
σ=pD2t⇒t=pD2σallow
Symbols in the formula
SymbolMeaningUnit
pInternal pressureMPa
DDiametermm
tWall thicknessmm
σallowAllowable stress of the steel at its temperatureMPa
Worked example
A shell against a tube at the same pressure
Given
  • Design pressure 10.54 kg/cm²(g) = 1.034 MPa. Allowable stress 120 MPa (illustrative).
  1. A 2,000 mm shell:
    t=1.034×2,0002×120=8.6 mm
  2. A 63.5 mm tube: 0.27 mm.
Answer: The same pressure needs a wall about 31 times thicker on the shell. That is why high pressures and large capacities need water tube construction, where every pressure-holding part is small in diameter.
ExpertThe fine print: where the simple model breaks, and what it costs.

Furnaces, tubes and how pressure parts fail

A shell boiler’s furnace tube is pressed from outside by the water around it, which tries to collapse it rather than burst it. A plain tube under external pressure buckles at a fraction of the load it could take from inside, so large furnaces are corrugated: the ridges stiffen the tube against collapse without making it thicker, and also let it expand along its length as it heats.

Pressure parts are cooled by the water on their other side, and almost every failure starts when that cooling is lost or weakened:

  • Overheating from low water: a furnace crown or tube uncovered by water heats far past its design temperature and bulges or ruptures.
  • Overheating from scale: a deposit on the water side insulates the metal, which then runs hotter than designed even with the water level correct.
  • Corrosion: oxygen pitting on the water side, acid attack on the gas side where gas cools below its dew point.
  • Fatigue and cracking: repeated heating and cooling, especially fast starts, cracks tube plates and ligaments between tube holes.
  • Leaking tube joints: tubes expanded into plates can loosen from thermal cycling.

Notice that the metal’s own temperature limit, not the steam’s, governs. Steel that is perfectly safe at 200 °C with water behind it can reach 500 °C or more under a flame without it, where its strength is a fraction of design. Module 12 covers tube failures in more detail.

Key takeaways

  • Pressure parts: shell or drums, furnace, tubes, tube plates and headers.
  • Hoop stress grows with pressure × diameter, so large shells need thick walls; small tubes do not.
  • Furnace tubes are corrugated to resist collapse from outside pressure.
  • Most failures start when the water side stops cooling the metal: low water, scale or corrosion.

Check your understanding

Questions run from beginner to expert. Try each before opening the answer.

  1. Beginner

    Q1. Which of these is a pressure part?

    1. A.Forced draft fan
    2. B.Steam drum
    3. C.Fuel conveyor
    4. D.Control panel
    Show answer

    B. The drum holds steam and water under pressure.

  2. Intermediate

    Q2. At the same pressure, doubling a cylinder’s diameter does what to the required wall thickness?

    1. A.Halves it
    2. B.No change
    3. C.Doubles it
    4. D.Quadruples it
    Show answer

    C. t = pD/2σ: thickness is proportional to diameter.

  3. Intermediate

    Q3. Why are shell boiler furnaces often corrugated?

    1. A.To look stronger
    2. B.To resist collapse under external pressure and allow expansion
    3. C.To burn more fuel
    4. D.To hold more water
    Show answer

    B. Corrugation stiffens the tube against buckling and lets it grow with heat.

  4. Expert

    Q4. Why does scale cause tube failures even when the water level is correct?

    1. A.It blocks steam flow
    2. B.It insulates the metal from the water, so the metal runs hotter than designed
    3. C.It adds weight
    4. D.It corrodes the gas side
    Show answer

    B. The metal loses its cooling and its strength falls with temperature.

Frequently asked

What are the pressure parts of a boiler?
The parts that contain steam and water under pressure: the shell or drums, furnace, fire or water tubes, tube plates, headers and the connecting pipework up to the stop valve.
Why are water tube boilers used for high pressure?
Wall thickness needed to hold pressure grows with diameter. Small-diameter water tubes and drums hold high pressure with practical thicknesses; a large shell would need impractically thick plate.

Related equipment

Training a boiler team?

These lessons follow the order we train operators in. We also run on-site operator and maintenance training, built around your own plant.

Boiler operator training →

Sources

  • Indian Boiler Regulations, 1950 — Design formulas for shells, drums, furnaces and tubes, including allowances and allowable stresses.

About the author

Shikhar SinghSteam Consultant & IT Consultant

Shikhar Singh is a Steam Consultant and IT Consultant at GyanTosh Fabricators Pvt. Ltd., where he works on steam system sizing, condensate recovery and the engineering content published on this site.

Full profile and background →